Water Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: January 2026 andFebruary 2026
(Base Month January 2010 =100)
Publish Date:25-03-2026
Click Here To Download Data as CSV File
| Major and Sup Groups | January 2026 | February 2026 | % Change |
| Water Reservoirs | 112.68 | 111.69 | -0.88 |
| Excavations | 127.56 | 127.72 | 0.12 |
| Concrete | 105.15 | 105.21 | 0.06 |
| Iron | 110.35 | 107.19 | -2.86 |
| Construction work and paint | 141.82 | 141.82 | 0.00 |
| Miscellaneous | 114.91 | 114.54 | -0.32 |
| Administrative expenses | 123.87 | 123.87 | 0.00 |
| Water Networks | 130.82 | 130.61 | -0.17 |
| Excavations | 127.56 | 127.72 | 0.12 |
| Deface Materials | 107.32 | 107.89 | 0.52 |
| Asphalt bitumen mixture and its products | 95.46 | 95.49 | 0.04 |
| Plastic and steel pipes | 142.17 | 141.47 | -0.49 |
| Administrative expenses | 123.87 | 123.87 | 0.00 |
| Wages and other costs | 157.84 | 157.84 | 0.00 |
| General index | 125.15 | 124.70 | -0.37 |