free hit counters
PCBS | Sewage Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: July 2025 and August 2025

Sewage Networks Cost Indices and Percent Changes by Major and Subgroups in the West Bank*: July 2025 and August 2025
(Base Month January 2010 =100)
Publish Date:28-09-2025
Click Here To Download Data as CSV File
Major and Sup GroupsJuly 2025August 2025% Change
Excavations129.60129.39-0.16
Deface Materials108.34107.84-0.46
Asphalt bitumen mixture and its products98.5998.57-0.02
Plastic and cements pipes117.84115.87-1.67
Fountains102.13101.05-1.06
Administrative expenses127.54127.540.00
Wages and other costs173.91173.910.00
General index118.18117.34-0.71

*Data exclude those parts of Jerusalem which were annexed by Israeli Occupation in 1967.
Close