Water Networks Cost Indices and Percent Changes by Major and Sub Group in the West Bank*: September 2022 and October 2022
(Base Month (January 2010 =100
Publish Date:24-11-2022
Click Here To Download Data as CSV File
Major and Sup Groups | September 2022 | October 2022 | % Change |
Water Reservoirs | 120.66 | 122.35 | 1.40 |
Excavations | 132.21 | 132.04 | -0.13 |
Concrete | 105.01 | 104.81 | -0.18 |
Iron | 134.46 | 140.09 | 4.18 |
Construction work and paint | 139.24 | 139.24 | 0.00 |
Miscellaneous | 115.52 | 115.24 | -0.24 |
Administrative expenses | 127.40 | 127.40 | 0.00 |
Water Networks | 132.50 | 132.19 | -0.23 |
Excavations | 132.21 | 132.04 | -0.13 |
Deface Materials | 102.54 | 102.79 | 0.24 |
Asphalt bitumen mixture and its products | 90.60 | 90.87 | 0.30 |
Plastic and steel pipes | 148.82 | 148.02 | -0.54 |
Administrative expenses | 127.40 | 127.40 | 0.00 |
Wages and other costs | 152.75 | 152.75 | 0.00 |
General index | 128.80 | 129.12 | 0.25 |