Construction Cost Indices and Percent Changes by Major Groups in the West Bank*: July 2022 and August 2022
(Base Year 2013=100)
Publish Date:25-09-2022
Click Here To Download Data as CSV File
Major Group | July 2022 Residential buildings | August 2022 Residential buildings | % Change Residential buildings | July 2022 Non-residential buildings | August 2022 Non-residential buildings | % Change Non-residential buildings | July 2022 Skeleton Buildings | August 2022 Skeleton Buildings | % Change Skeleton Buildings |
Raw materials | 112.38 | 111.79 | -0.53 | 111.60 | 111.06 | -0.48 | 112.50 | 111.28 | -1.08 |
Hiring of equipment | 106.03 | 105.62 | -0.39 | 106.37 | 106.09 | -0.27 | 106.07 | 105.67 | -0.37 |
Labour cost and wages? | 138.97 | 141.09 | 1.52 | 138.97 | 141.09 | 1.52 | 144.81 | 146.39 | 1.09 |
General Index | 119.39 | 119.51 | 0.09 | 118.56 | 118.67 | 0.10 | 120.03 | 119.53 | -0.42 |