Sewage Networks Cost Indices and Percent Changes by Major and Sub Groups in the West Bank*: November and December 2018
(Base Month January 2010=100)
click Here To Download Excel File |
|||
Major and Sup Groups |
November 2018 |
December 2018 |
% Change |
Excavations |
123.79 |
124.19 |
0.32 |
Deface Materials |
103.08 |
103.01 |
-0.07 |
Asphalt, bitumen mixture and its products |
90.47 |
86.07 |
-4.86 |
Plastic and cements pipes |
101.38 |
101.50 |
0.12 |
Fountains |
108.65 |
108.40 |
-0.23 |
Administrative expenses |
119.34 |
119.37 |
0.02 |
Wages and other costs |
139.87 |
138.16 |
-1.23 |
General index |
109.75 |
109.33 |
-0.38 |
*Data exclude those parts of Jerusalem which were annexed by Israeli Occupation in 1967. |