Construction Cost Indices and percent changes for Residential, Non-Residential and Skeleton buildings by Major Groups in the West Bank* for the years 2018 and 2017

 (Base Year 2013=100)

 

click Here To Download Excel File

Major Groups 

Residential buildings

Non-residential buildings

Skeleton Buildings

Avg. 2017

Avg. 2018

% Change

Avg. 2017

Avg. 2018

% Change

Avg. 2017

Avg. 2018

% Change

Raw materials

98.46

100.49

2.07

98.89

100.77

1.90

96.19

100.03

4.00

Hiring of equipment

101.20

101.54

0.34

101.73

102.06

0.33

102.21

102.51

0.29

Labour cost and wages 

117.29

118.40

0.94

117.29

118.40

0.94

120.74

121.43

0.58

All- Items Construction Cost Index

104.15

105.84

1.63

104.16

105.78

1.55

102.61

105.53

2.84


*Data excluded those parts of Jerusalem which were annexed by Israeli Occupation in 1967.