Water Networks Cost Indices by Major and Sub Groups in the West Bank* for the Years 2018 and 2017
(Base Month January 2010=100)
click Here To Download Excel File |
|||
Major and Sub Groups |
West Bank |
||
Average 2017 |
Average 2018 |
% Change |
|
Water Reservoirs |
105.24 |
109.78 |
4.31 |
Excavations |
124.53 |
125.50 |
0.78 |
Concrete |
104.83 |
104.39 |
-0.42 |
Iron |
95.92 |
109.59 |
14.25 |
Construction work and paint |
119.35 |
121.19 |
1.54 |
Miscellaneous |
107.11 |
107.40 |
0.28 |
Administrative expenses |
115.72 |
118.57 |
2.46 |
Water Networks |
114.96 |
115.78 |
0.71 |
Excavations |
124.53 |
125.50 |
0.78 |
Deface Materials |
101.66 |
102.68 |
1.01 |
Asphalt, bitumen mixture and its products |
85.04 |
87.05 |
2.37 |
Plastic and steel Pipes |
122.02 |
121.13 |
-0.73 |
Administrative expenses |
115.72 |
118.57 |
2.46 |
Wages and other costs |
127.73 |
132.22 |
3.51 |
General index |
111.92 |
113.90 |
1.77 |
*Data excluded those parts of Jerusalem which were annexed by Israeli Occupation in 1967. |