Sewage Networks Cost Indices by Major and Sub Groups in the West Bank for the Years 2019 and 2018

(Base Month January 2010=100)

 

Click Here To Download Excel File

Major and Sub Groups 

Avg. 2018

Avg. 2019

% Change

Excavations

125.50

123.84

-1.33

Deface Materials

102.68

102.55

-0.12

Asphalt, bitumen mixture and its products

87.05

87.41

0.41

Plastic and Cements Pipes

101.65

102.26

0.59

Fountains

107.63

108.89

1.17

Administrative expenses

118.57

119.42

0.71

Wages and other costs

139.82

140.78

0.68

General  index

109.51

109.78

0.25


*Data excluded those parts of Jerusalem which were annexed by Israeli Occupation in 1967.